Course outline / Financial functions

Lesson 70 of 75 · Advanced · 3 exercises

Is an investment worth it?

Net present value, internal rate of return and payback.

Start this lesson free

What you'll practise

  1. Net present value with NPV
  2. Internal rate of return with IRR
  3. Simple profit

Net present value with NPV

Money later is worth less than money now. NPV discounts future cash flows back to today at a chosen rate.

NPV treats its first value as arriving after one year, so leave the year-0 investment out and add it separately:

=NPV(rate, year1:yearN) + year0

In cell E2, work out NPV(D2, B3:B6) + B2.

Internal rate of return with IRR

IRR is the rate at which NPV is exactly zero: the project's own rate of return. If it beats your required rate, the project is worth doing.

IRR includes the year-0 cash flow in its range.

In cell E2, work out IRR(B2:B6).

Simple profit

Before discounting, check the simple total.

In cell E2, add up all the cash flows in B2:B6.

Try it in a real spreadsheet

Every step checks your answer instantly and tells you exactly what to fix.

Start the lesson

Function guides

← Interest rates comparedDepreciation →