Weekdays and working days
Find the day of the week, add working days, and count them.
What you'll practise
- Day of the week as a number
- Is it a weekend?
- Add working days with WORKDAY
- Count working days
Day of the week as a number
WEEKDAY returns a number for the day of the week. With 2 as the second argument, Monday is 1 and Sunday is 7, which is easy to read.
In cell D2, find the weekday number of A2, Monday = 1.
Is it a weekend?
With Monday as 1, Saturday is 6 and Sunday is 7, so a weekend day has WEEKDAY(date,2) greater than 5.
In cell D2, show "Weekend" if B2 falls on a weekend, otherwise "Weekday".
Add working days with WORKDAY
WORKDAY adds a number of working days to a date, skipping weekends.
In cell E2, find the date 10 working days after A2.
Count working days
In cell D2, count the working days from A2 to B2 with NETWORKDAYS.